NEWS / Infrastructure Intelligence / Second HS2 tunnelling machine completes five-mile drive under London

Final tunnel ring segments being installed
Image: HS2

03 APR 2025

SECOND HS2 TUNNELLING MACHINE COMPLETES FIVE-MILE DRIVE UNDER LONDON

HS2 has today (3 April) completed a five-mile tunnel drive under London – using one of four giant tunnelling machines being used to build the railway’s Northolt Tunnel.

The tunnel boring machine (TBM), named Caroline, is the second machine to reach the Green Park Way vent shaft in Ealing.

The 2,050-tonne TBM broke through into an underground reception can filled with foam concrete, and installed the 4,217th concrete tunnel ring to complete the five-mile stretch of tunnel.

Due to high water pressure in the ground at the site, HS2 is using the reception can method for the breakthrough of the machines.

The reception can allows the TBM to maintain pressure while sealant can be applied from the tunnel lining, preventing water ingress. The reception can is then depressurised before it is opened and the TBM is lifted out.

A quartet of TBMs are being used to build the Northolt Tunnel – an 8.4-mile twin bore tunnel that will take brand new high-speed trains from the outer edge of the capital at West Ruislip into the new Old Oak Common super-hub station in west London.

Two machines, including Caroline, have been used to build the western section of the tunnel while two more excavate the eastern leg – all being lifted out of the ground at Green Park Way.

Launched in October 2022, TBM Caroline has completed her drive with teams working around the clock to operate the machine.

It excavates the earth and installs the concrete segments that make up the rings to form the tunnel.

The TBM was named by school children from Brentside Primary Academy in Ealing after 18th century astronomer Caroline Herschel.

The first machine to be launched for this stretch of the HS2 route, Sushila, completed her journey in January and has subsequently been lifted out from the ground at Green Park Way.

Two further machines are currently building the eastern section of the tunnel from HS2’s Victoria Road Crossover Box just outside of the Old Oak Common station site. In total 93% of the Northolt tunnel has now been built, and the two further machines will complete their journeys later this year.

Work on construction of the new high-speed continues as Mark Wild, chief executive of HS2, undertakes a comprehensive review of the project. His work will lead to a fundamental reset the programme.

HS2’s London tunnels contractor, Skanska Costain STRABAG joint venture (SCS), is responsible for building the HS2 route through London.

Richard Adams, managing director for Skanska Costain STRABAG joint venture, said: “The arrival of TBM Caroline at Green Park Way marks a significant milestone – the completion of the western section of the Northolt Tunnel – and is a testament to the dedication and skill of all our teams.

“Later this year two more TBMs, Emily and Anne, will finish their journeys, which will complete the 8.4-mile Northolt tunnel between Old Oak Common and West Ruislip.

“Work on the cross passages, tunnel walkways, ventilation shafts, headhouses and portals continues at pace as our team works at peak productivity to deliver our part of HS2, that will bring better journeys and boost economic growth.”

Now that the two western TBMs have completed their journeys, SCS JV will continue to work in the five-mile stretch of the Northolt Tunnel to construct 20 cross-passages which run between the two tunnel bores.

In total, five deep, twin-bore tunnels are being built for HS2 between London and the West Midlands.

 

INDUSTRY NEWS THAT MIGHT INTEREST YOU

;